Bruno Company accumulates the given data concerning a mixed cost, by using miles as the activity level.

MONTH---------Miles Driven------Total Cost

January----------8,000----------------$14,150

February--------7,500----------------$13,500

March-----------8,500----------------$15,000

April-------------8,200----------------$14,490

Calculate the variable and fixed cost elements by using the high low method.