Utilizing the step-by-step mrp calculation process students


Utilizing the Step-by-Step MRP Calculation Process, students will solve the following MRP problem given: Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. Product C is made of two units of F and two of E. Product A has a lead-time of one week. Products B, C and E have lead-times of two weeks. Products D and F have a lead-time of three weeks.

*Create an Master Production Schedule and a Material Requirement Planning Chart

*If there is a positive net requirement in a week, backward schedule by the lead-time and enter the quantity for the planned order release that will satisfy the net requirement.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Utilizing the step-by-step mrp calculation process students
Reference No:- TGS02731337

Now Priced at $30 (50% Discount)

Recommended (95%)

Rated (4.7/5)