task | planned starting month | planned duration (months) | actual starting month | actualduration(mths) |
A |
1 |
2 |
2 |
3 |
B |
2 |
3 |
3 |
5 |
C |
4 |
3 |
6 |
3 SO FAR |
D |
6 |
5 |
7 |
2 SO FAR |
E |
8 |
4 |
NOT YET BEGUN |
|
F |
10 |
3 |
NOT YET BEGUN |
|
Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance