Question: Consider the following time series data:
Week 1 2 3 4 5 6
Value 18 13 16 11 17 14
Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy:
a. Mean absolute error
b. Mean squared error
c. Mean absolute percentage error
d. What is the forecast for week 7?