Using the mrp forms - create the mrp tables for all parts


I need an expert in OM to do this MRP assignment

BIS 312 - Excel, MRP

846_Create the MRP tables for all parts.png

Forecasted demand for cabinets:
Week 4: 100 Week 7:100 Week 10: 100

Item  Beginning Inventory  Scheduled Receipts  Lot Size Rule  LT 
CD Cabinet   0 None  L4L  1
Cabinet Top  120 None  FOQ= 144  3
Cabinet Bottom  20 Week 3- 144  FOQ = 144  3
Cabinet Door  120 Week 3- 216  FOQ= 216  3
Cabinet Sides  0 Week 3- 216  FOQ=216  3
Cabinet Shelves  0 None  L4L  2
Shelf Supports  0 None  FOQ=2500  1
Door Magnet  12 None  FOQ= 250  2
Door Hinge  0 Week 3- 932  FOQ=932  4
Door Handle  50 Week 3- 200  FOQ=200  3
Door Screws  500 None  FOQ=2000  1
Door Catch  0 None  FOQ=252  1
Feet  0 Week 3- 576  L4L  4

Using the MRP Forms I posted, create the MRP tables for all parts of the CD cabinet for a 12 week planning period.

Note: You need to adjust the forms to work with this assignment by adding the required information

Attachment:- Template.xlsx

Solution Preview :

Prepared by a verified Expert
Operation Management: Using the mrp forms - create the mrp tables for all parts
Reference No:- TGS01146049

Now Priced at $35 (50% Discount)