Problem 1:
Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks:
The critical path is A-B-D-G-H.
(a) Calculate the probability of completing the project in 36 weeks.
P(project ≤ 36) =
(b) Calculate the probability of completing the project in 40 weeks.
P(project ≤ 40) =
(Round your answers to 3 decimal places, the tolerance is +/-0.005.)