Question: Using the information in Table, balance the assembly line for the Tourist T-Shirt Company. The operations run continuously for eight hours per day. Each day, 80 T-shirts must be produced to meet customer demand.
a. Draw the precedence diagram.
b. What is the takt time?
c. What are the theoretical number of workstations?
d. Assign tasks to workstations using the longest task time rule.
e. What is the efficiency of the balanced line?