Question: Using the information in Problem, highlight the project's status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print the output file.
Problem: Use the following information to construct a tracking Gantt chart using MS Project.
![927_Activities.png](https://secure.tutorsglobe.com/CMSImages/927_Activities.png)
Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print the output file.