Using the information from the Glendale Stadium Project (end of Chapter 6), you will create a MS Project schedule and answer the questions from the end of the case, however, you will note the following changes: •The crew work only Monday – Fridays (no weekend work) 8 hours per day. • Employees are giving off the following days: Good Friday; Good Monday; Friday before Memorial Day; Memorial Day; July 3-5; Friday before Labor Day; Labor Day; the entire week of Thanksgiving ; and the period of December 24 – January 2