Using the data in Table 13-4, determine the latest time activity A can be finished and not delay any activity? Table 13-4 The following represents a project with known activity times. All times are in weeks Activity Immediate Predecessor Time A - 4 B - 3 C A 2 D B 7 E C, D 4 F B 5 G E, F 4 Which Answer is it 4 0 8 5 none of the above