Using the data in Table 13-1, what is the latest possible time that C may be started without delaying completion of the project? Table 13-1 The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor TIme A - 4 B - 3 C A 2 D B 7 E C, D 4 F B 5 which Answer is it 0 4 8 10 none of the above