Using Earned Value Management in projects, multi-functional control account plans should have:
A. A point of Management control from WBS, Homogenous Work scope, Multiple Functions, and Earned Value Performance Measured
B. A Precise Scope of work, a Schedule, a Budget, and a CAP Manager
C. Organizational Breakdown Structure, Work Breakdown Structure, Control Account Plans, and Points of Management Control
D. None of the above