Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path. How long is the minimum duration of this network?
Activity
|
Nodes
|
Time (weeks)
|
Activity
|
Nodes
|
Time (weeks)
|
J
|
1-2
|
10
|
N
|
3-4
|
2
|
K
|
1-3
|
8
|
O
|
4-5
|
7
|
L
|
2-4
|
6
|
P
|
3-5
|
5
|
M
|
2-3
|
3
|
|
|
|