Case Study: "The Wedding"
Using a project start time of 0 (or January, 1) and a required project completion time of 180 days (or June, 30), calculate the ES, EF, LS, and LF times and total slack for each activity. If your calaculations result in a project schedule with negative total slack, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an acceptable baseline schedule for completeing the project within 180 days (or by June 15). Describe the revisions you would make.