Question - For each of the six different costs (A, B, .... , F} given belong Indicate whether It la a variable, fixed, or mixed coat with regard to machine hours. Use the high-low technique to estimate the variable cost per machine hour and the total fixed costs for each.
Cost
|
100 hours
|
125 hours
|
A
|
$1,000
|
$1,000
|
B
|
$4,000
|
$5,000
|
C
|
$14,000
|
$14,0000
|
D
|
$9,000
|
$11,250
|
E
|
$10,000
|
$12,000
|
F
|
$5,000
|
$6,250
|