Use MS Project to schedule the construction activities logically. Identify the critical path
Activity Name |
Duration (Days) |
Office Building Project |
|
Submission/Approvals/Permits |
|
Structural Steel Submittal |
20 |
HVAC Submittals |
15 |
MEP Coordination |
10 |
Obtain Temp CO (Certificate of Occupancy) |
2 |
Plumbing Inspections |
5 |
Electrical Inspections |
7 |
Electrical Utility Company Coordination/ Tie ins |
20 |
Gas Utility Company Coordiation/ Tie ins |
9 |
Water Utility Company Coordination/ Tie ins |
8 |
Foundation |
|
Site Clearing |
10 |
Footing Excavation |
20 |
Install Storm Sewer & Manholes/Inlets |
10 |
Install Sanitary Sewer & Manholes |
10 |
Install Underground Water Lines |
5 |
Install Underground Electric Conduit |
5 |
Form/Pour Concrete Footings |
20 |
Form and Pour Column Piers |
15 |
Form and Pour Bassment Slab |
10 |
Backfill and Compact Footings |
5 |
Structure |
|
Fabricate Structural Steel |
45 |
Erect Structural Frame |
35 |
Floor Decking (1st & 2nd Floors) |
22 |
Pour First Floor Slab |
12 |
Erect Stairwell and Elevator Walls |
15 |
Pour Second Floor Slab |
12 |
Erect Roof Trusses |
7 |
Plumbing and Electrical |
|
HVAC First/Second Floors |
20 |
Rough-In Eelctrical |
15 |
Rough-In Plumbing/Piping |
11 |
Install Wiring and Cable |
25 |
Gas Piping Installs |
18 |
Connect Equipment |
2 |
Exterior Finishes |
|
Brickface Exterior Walls |
36 |
Roof |
|
Insulation and Built-up Ply Roofing |
21 |
Doors and Windows |
|
Install Door and Window Frames |
6 |
Install Exterior Doors and Windows |
9 |
Install Interior Doors |
4 |
Interior Finishes |
|
Drywall in Offices |
36 |
Flooring & Carpeting |
20 |
Paint Building Interior |
22 |
Plumbing and Lighting Fixtures |
|
Install Lighting Fixtures |
10 |
Install Plumbing Fixtures |
10 |
Paving & Landcaping |
|
Install & Compact Subgrade |
14 |
Curbing, including Excavaton/Form/Pouring |
16 |
Install Asphalt Base Course |
3 |
Install Asphalt Surface Course |
2 |
Linestriping and Signage |
5 |
Landscaping |
5 |
Punch List |
5 |