Use a multiple activity chart to illustrate how one operator can tend machine A and machine B during a repeating cycle, based on the following data: a = 2 min, b = 1 min, t = 6 min. What is the length of the repeating cycle? (Hint: The multiple activity chart will need to cover at least the first 20 minutes of the operation)