Unizat Corporation uses the weighted-average method in its process costing system. The following information pertains to one of the company's processing departments for a recent month:
![2224_Lowler Corporation6.png](https://secure.tutorsglobe.com/CMSImages/2224_Lowler%20Corporation6.png)
All materials are added at the beginning of the process. The cost per equivalent unit for materials is closest to:
Answer
$0.86
$0.90
$1.10
$1.18