Tyro Co. uses a standard cost system. The subsequent information pertains to direct labor for product B for the month of May:
Actual rate paid $8.40 per hour
Standard rate $8.00 per hour
Standard hours allowed for actual production 2,000 hours
Labor efficiency variance $ 800 unfavorable
Find what were actual hours worked?