Straightforward variance analysis
Arrow Enterprises uses a standard costing system. The standard cost sheet for product no. 549 follows.
Direct materials: 4 units @ $6.50
|
|
$26.00
|
Direct labor: 8 hours @ $8.50
|
|
68
|
Variable factory overhead: 8 hours
|
@ $7.00
|
56
|
Fixed factory overhead: 8 hours
|
@ 2.5
|
20
|
Total standard cost per unit
|
|
$170.00
|
The following information pertains to activity for December:
1. Direct materials acquired during the month amounted to 26,350 units at $6.40 per unit. All materials were consumed in operations.
2. Arrow incurred an average wage rate of $8.75 for 51,400 hours of activity.
3. Total overhead incurred amounted to $508,400. Budgeted fixed overhead totals $1.8 million and is spread evenly throughout the year.
4. Actual production amounted to 6,500 completed units.
Instructions:
a. Compute Arrow's direct material variances.
b. Compute Arrow's direct labor variances.
c. Compute Arrow's variances for factory overhead.