A firm is reviewing a project with labor cost of $6.60 per unit, raw materials cost of $22.85 a unit, and fixed costs of $13,000 a month. Sales are projected at 8,600 units over the 3-month life of the project.
Required:
Question: What are the total variable costs of the project?