Problem:
Reddy Company has the following cost formulas for overhead:
Cost Cost Formula
Indirect materials $2,000 plus $0.40 per machine hour
Maintenance $1,500 plus $0.60 per machine hour
Machine setup $0.30 per machine hour
Utilities $200 plus $0.10 per machine hour
Depreciation $800
Based on these cost formulas, the total overhead cost at 600 machine hours is expected to be:
A) $4,500. C) $5,620.
B) $5,200. D) $5,340.