Dale Company, which applies overhead at the rate of 190% of direct labor cost, began work on job no. 101 during June. The job was completed in July and sold during August, having accumulated direct material and labor charges of $27,000 and $15,000, respectively. On the basis of this information, the total overhead applied to job no. 101 amounted to:
A. $0.
B. $28,500.
C. $51,300.
D. $70,500.
E. $79,800.