Total cost for the job on the job cost sheet


The following data have been recorded for recently completed Job 501 on its job cost sheet. Direct materials cost was $3,127. A total of 42 direct labor-hours and 116 machine-hours were worked on the job. The direct labor wage rate is $12 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine-hour. The total cost for the job on its job cost sheet would be: