Toliara operates? two-eight hour shifts per day. Downtime for? lunches, breaks and equipment? set-ups equals a total of 1.50 hours for the 24 hour operating day. Annual customer demand is? 69,310 units and Toliara operates 239 days per year. ?Toliara’s production process uses eight work cells to complete the production process. Each work cell requires 3 minutes to complete the production work per cell. What is the cycle time in? seconds?
A. 480
B. ?1,440
C. 240
D. ?3,600