To manage procurement risk procurement manager john has a


 To manage procurement risk, Procurement Manager John has a policy of only using experienced, dependable, and proven sellers instead of selecting sellers through open competition. What risk management technique is John using here?

A. Risk Acceptance.

B. Risk Mitigation.

C. Risk Transfer

D. Risk Avoidance.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: To manage procurement risk procurement manager john has a
Reference No:- TGS01508947

Expected delivery within 24 Hours