To control your project, you decide to use milestone analysis. Which of the below is not a benefit of using milestone analysis to control a project?
A. Milestones eliminate unnecessary changes to a project.
B. Milestones align schedules with suppliers.
C. Milestones trigger other team members’ participation in the project.
D. Milestones allow for periodic review of the project.