To construct an electricity generating unit, a company has to install 80 items. One team takes on an average 20 days to install one item. A team works for 300 days/year and management wants each team to have a capacity cushion 60 days per year. How many teams have to be deployed by the company to complete the project in one year. Be sure to round any decimal in your answer UP to the next whole integer