Time minimizing assignment problem


A professor has been contacted by the four not-for-profit agencies which are willing to work with student consulting teams.  The agencies need aid with such things as budgeting, information systems, coordinating volunteers, and forecasting. Although each of four student teams could work with any of agencies, the professor feels that there is the difference in amount of time it would take each group to solve each problem.  The professor's estimate of time, in days, is given in table below. Use Management Science Cd to determine which team works with which project.

 

Projects

Team

Budgeting

Information

Volunteers

Forecasting

A

32

35

15

27

B

38

40

18

35

C

41

42

21

38

D

45

15

30

24

1. In optimal solution, determine the minimum time needed to complete project?

2. In the optimal solution, who does Team B work with?

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Time minimizing assignment problem