Question: Ricric Corporation has provided the following data for one of its products:

Process time 3 days
Queue time 4 days
Inspection time 0.7 days
Move time 0.3 days
Wait time 9 days

Q. The throughput time for this operation would be:

A) 8 days. C) 17 days.