This chart lists the estimated lengths and arrival times for 5 jobs.
? In what order do these run using FCFS?
? What is the average turn-around time (difference in time between a job's arrival and its completion)?
? In what order do they run using SJF?
? What is the average turn-around time using SJF?
Job Length Arrival
A 9 0
B 6 0
C 3 5
D 5 5
E 4 10