You are a systems analyst at DelCore Corporation and you are a project leader of a team that is developing a new production monitoring system for a client. Your team completed the unit testing and the integration testing and is preparing to start the system testing which is scheduled for the next three weeks. Your manager, Yosemite Sam, who is under a lot of management pressure, wants to deliver the system to the client within several days. He approached you and asked if you could trim system testing from three weeks to five days. Your manager requested that you write to him a brief memo expressing your views.
Question: As a system analyst, you know that this is not a good decision. Therefore, what do you include in your brief memo regarding your manager's decision to trim down the system testing time? What are your views concerning this request?