There may be more than one critical path in a project


Which one of the following statements is ?false?

A. There may be more than one critical path in a project network.

B. The critical path is the sequence of activities between a? project's start and finish that takes the shortest time to complete.

C. If one of the activities on the critical path is? delayed, the entire project will be delayed.

D. The activities along the critical path determine the completion time of the project