The Project Manager
There is a £1,000 per week penalty for each week the project is delayed beyond week 25. Indirect costs relevant to this project are £2,500 per week.
Identify recommended completion week, and the savings..
Use bullet points to highlight the major benefits and limitations of applying this ‘crash’ analysis to Project Management.