The XYZ Company wants to establish kanbans to feed a newly installed work cell. The daily production (demand) rate is 170 units. The production lead time is 3 days. They want to keep a 25% buffer of safety stock on hand (the safety stock factor). The kanban size is 35 units. How many kanbans do they require?