“The way the company made all these estimates is by conducting a technical and economic feasibility study that cost $35,000. It also cost $15,000 to develop and market test the new nuggets” Would the 35000 be considered sunk bc you’re spending it regardless of accepting or rejecting the project? So would you only include the 15,000 in the Net initial investment?