You have a network with a critical path A-B-C-D. For our purposes, you are allowed to ignore the other paths through the network. The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below. These are based on the probability that virtually all (at least 99.7%) of the values of each task fall within the range from a to b.