The ultimate consolidation of a 13-ft thick single-drained clay layer (cv = 0.1 ft2/day) was calculated to be 0.813 feet.
a) How much settlement would you expect after 10 months?
b) What is the degree of consolidation if the fill has already settled 0.5-feet?