1. The two dominant components of acquisition management are program management and:
process management
project management
quality management
contract management
2. In EVMS, the term surveillance refers to:
a. a careful tracking of budget and schedule performance
b. a process of validating a contractor's compliance with EVMS requirements
c. an audit carried out to assure that a contractor is honest in its claims for reimbursement for expenses incurred
d. a review of the adequacy of security at a contractor's facilities.