As the Purchasing Agent of Alliance Airlines, you are aware that the fifth plane you are about to receive took 22,500 labor hours to assemble. If the labor charge is $65.00 per hour and you estimate a learning curve of 85%, Calculate:
1. The labor hours to assemble airplane number seven
2. The total labor cost to assemble the first eight airplanes