The time required for one team of employees to produce the first item is 100 hours. The learning curve percentage for unit number 70 is established to be 88%. At unit 71 the team of employees changes, while the time needed for the production of unit 71 increases by 10% when compared to the time needed for unit number 70. If the learning curve percentage for the new team of employees is 92%, what amount of time will they need to produce unit number 130?