The three-station work cell illustrated in Figure S7.7, has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2.

Station 1 Machine A Capacity: 20 units/hr

Station 1 Machine B Capacity: 20 units/hr

Station 2 Capacity: 5 units/hr

Station 3 Capacity: 12 units/hr

a) what is the bottleneck time of the system?

b) what is the bottleneck station of this work cell?

c) what is the throughput time?

d) if the firm operates 10 hrs per day, 5 days per week, what is the weekly capacity of this work cell?