The three dimensions of performance in Earned Value Project Management are:
A) Actual Cost, Earned Value, and Schedule Variance
B) Actual Cost, Planned Value, and Scheduled Variance
C) Cost Variance, Planned Value, and Schedule Variance
D) Actual Cost, Earned Value, and Planned Value