The teams then compared the resulting work breakdown


Two IT acquisition planning teams worked together to study the same problem and develop alternative solutions for solving it. The teams then separated and each developed a work breakdown structure for the same alternative solution.

The teams then compared the resulting work breakdown structures and found that they were significantly different. Is only one of the work breakdown structures correct? Could both be correct? Could both be incorrect?