The standards for direct labor for a product are 5 hours at $10 per hour. Last month, 9,100 units of the product were made and the labor efficiency variance was $8,100 F. The actual number of hours worked during the past period was:
A. 45,500
B. 46,500
C. 43,690
D. 44,690