Problem
The standard direct labor cost per unit for a company was $32 (= $20 per hour × 1.6 hours per unit). During the period, actual direct labor costs amounted to $188,800, 9,600 labor-hours were worked, and 5,000 units were produced.
Required:
Compute the direct labor price and efficiency variances for the period.