A shopkeeper keeps 60 cases of safety stock to be assured of meeting his customer demand during lead time 90% of the time. His supplier takes 9 days to deliver. The standard deviation of demand is about 15 cases/day. How would his service probability change if he cut his safety stock by 10 units?