A project is 40% complete. Cost, schedule, and scope baselines are all being met. Two crucial stakeholders approach you with a request to implement a new software package that could significantly impact external interfaces. The software in question had been previously discussed prior to baselining the project scope, and is listed as a denied requirement in project documentation. What should the project manager do to resolve the situation with the stakeholders?