The Shady Farm Milk Company can process milk at a fixed rate of 7900 gallons/hour. the company's clients request 110000 gallons of milk over the course of one day. This demand is spread out uniformly from 8 a.m. - 6 p.m. the company starts producing at 8 a.m. and continues to work until all of the demand has been satisfied.
At noon, how many gallons of milk are in the queue to be processed?