The Shady Farm Milk Company can process milk at a fixed rate of 7100 gallons/hour. The company’s clients request 93000 gallons of milk over the course of one day. This demand is spread out uniformly from 8 a.m. - 6 p.m. The company starts producing at 8 a.m. and continues to work until all of the demand has been satisfied. At noon, how many gallons of milk are in the queue to be processed? _________gallons.